An electrical tender pack gives contractors the information they need to price the same job. Without one, a low quote may reflect missing work rather than better value. Clear drawings, a defined scope and a shared return format make differences easier to spot.
This checklist helps developers and main contractors prepare a useful enquiry before requesting prices. It covers what to issue, which responsibilities to settle and how to handle gaps. Electrical design and technical decisions should remain with the people appointed and competent to make them.

Start your electrical tender pack with a clear brief
First, describe the project in a short cover sheet. Include the site address, building use, number of units and current design stage. Also name the person who will answer questions and give a realistic tender return date.
Explain whether you want a budget estimate or a price against a developed design. These are different requests. If layouts or equipment choices remain open, identify them clearly instead of asking contractors to guess.
For example, a housing scheme may still need a final kitchen appliance schedule. In that case, request a stated allowance and list the information needed to replace it with a firm price.
Issue drawings that agree with each other
Next, gather the latest architectural and electrical information in one place. Use a drawing register so each contractor can see the issue date and revision. Remove superseded files from the pricing folder.
Your pack may need:
- Floor plans with consistent room names and dimensions.
- Lighting, switch and socket layouts.
- Equipment schedules showing electrical connection requirements.
- Plant room, riser and ceiling coordination drawings.
- Site layouts for external lighting and supplies.
Where the design is incomplete, flag the missing detail. For instance, a socket symbol does not explain whether the accessory is standard white plastic or a specified decorative finish. A short schedule can settle that question before pricing begins.
Define the scope and design responsibilities
Set out what the contractor must design, supply, install, test and hand over. Then list work by others. This prevents a vague phrase such as “complete electrical installation” from carrying different meanings for each bidder.
The HSE explains that an electrician who designs an installation can have designer duties. Therefore, identify who owns each design task rather than assuming the tender itself resolves responsibility.
Also check the boundaries between trades. Who supplies the ventilation equipment? Confirm who connects it, too. Then assign control wiring, access panels and fire stopping around service openings. Record an agreed answer for each relevant item.
Complete Connectrix provides residential electrical services for new builds and other residential projects. A defined scope helps the team understand which parts of your scheme the enquiry covers.
Add site information and a workable programme
An electrical tender pack should explain the conditions behind the drawings. Include access arrangements, working hours, delivery restrictions and available storage. For phased developments, show when each plot or block will be ready.
For commercial clients, HSE guidance on CDM duties requires pre-construction information for contractors and designers bidding for the work. It also calls for sufficient time and resources. A tender checklist supports that process; it does not replace the client’s wider duties.
Then set out key dates for first fix, second fix, testing and handover. Ask bidders to identify dependencies, including access by other trades or delivery of specified equipment. This makes programme assumptions visible before you appoint anyone.
Compare electrical tender prices consistently
Next, give every contractor the same pricing headings. A total alone makes it difficult to see whether two offers cover the same work.
Useful headings include installation areas, major systems, testing and handover. Also request separate entries for provisional allowances and optional upgrades. Ask each bidder to state exclusions, lead times, quote validity and any assumptions affecting the price.
For example, keep a proposed decorative lighting upgrade separate from the base specification. Otherwise, one contractor may include it while another prices standard fittings. You can then compare the base work fairly before considering alternatives.
Avoid choosing solely on the lowest figure. Instead, review the scope, programme, relevant capability and outstanding questions together.
Control questions and document changes
Once the enquiry is out, keep a shared clarification log. Give each question a reference and circulate answers that affect pricing to all tenderers. As a result, everyone works from the same information.
If the design changes, issue a dated amendment with a clear description. State which drawing or schedule it replaces. Then ask contractors to confirm that their return includes that revision.
Before accepting a quote, resolve qualifications that change the job. “Subject to survey” or “builder to provide access” may be reasonable, but the practical meaning needs agreement. Record the decision alongside the accepted scope.
Check your electrical tender pack before sending
Finally, review the pack as if you were seeing the project for the first time. Can a contractor understand the building, the required work and the basis for pricing without a separate verbal explanation?
Check these final items:
- Drawings and schedules carry matching revisions.
- Design duties and work by others have named owners.
- Site constraints and key dates appear in the brief.
- The pricing form separates allowances and options.
- Testing, records and handover requirements are clear.
Keep one issued copy of the electrical tender pack with its clarification log. That gives your project team a clear reference when comparing returns and agreeing the appointment.